August construction update

31 August 2020

The Strathalan construction site at Erskine Road, Macleod is progressing well, with 37 contemporary new retirement apartments. Our builders have completed a great deal of work in August – winter weather notwithstanding – and you can see the fruits of their labour in our video. Here’s a recap of the key construction work that’s been done at Strathalan Macleod in the past month:

  • Waterproofing of all apartment bathrooms
  • Apartment bathroom tiling commenced
  • Apartment windows installed
  • Shared spaces window installation has begun.

Over the next month, there is plenty of work scheduled at Strathalan. Some of the key works include:

  • Rough-in of services
  • Framing works
  • Installation of door frames
  • Ongoing plasterboard sheeting
  • Ongoing tiling of apartment bathrooms
  • Commencement of joinery installation.

It’s all very exciting and we’re well on track to welcoming our first residents early in 2021. For a real bird’s eye view of the Strathalan construction site, don’t forget to watch our video.

Strathalan is open for inspection between 10am and 4pm Mondays, Wednesdays and Fridays. Some rules and social distancing protocols apply. Complete the form and our Sales Manager will contact you very soon to provide any further information you require. Alternatively, call us on 8458 5437.